What will be the average number of jobs in the system


Problem:

The Budd Gear Co. specializes in heat-treating gears for automobile companies. At 8:00 a.m., when Budd's shop opened today, five orders (listed in order of arrival) were waiting to be processed.

Order Order Size
(units)
Per Unit Time in
Heat Treatment
(minutes/unit)
Due Date
(min. from now)
A 16         4             160
B 6         12             200
C 10         3             180
D 8         10             190
E 4         1             220
 

Required:

Question 1) If the due date rule is used, what sequence should be used?

Question 2) What will be the average job tardiness? (Round your answer to 2 decimal places.)

 

Question 3) What will be the average number of jobs in the system? (Round your answer to 2 decimal places.)

Question 4) Would the Shortest processing time rule produce better results in terms of average job tardiness?

Solve the given numerical problem and illustrate step by step calculation.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What will be the average number of jobs in the system
Reference No:- TGS0880686

Expected delivery within 24 Hours