What is the total price


Homework

Answer/complete both of the following two questions. Submit your work products through the appropriate homeworks folder by the close of the session. Ensure each file you post includes your last name in the file name.

Question I: Your firm designs training materials for computer training classes, and you have just received a request to bid on a contract to produce a complete set of training manuals for an 8-session class. From previous experience, you know that your firm follows a90% learning rate. For this contract, it appears that the effort will be substantial, running 400 hours for the first session. Your firm has an average cost of labor of $60/hour and the overhead is expected to run a fixed $1000per session. The customer will pay you a flat fixed rate per session (Per Session Price.) If your profit markup is 12%, what will be the Total Price, the Per Session Price, and at what session will you break even?

Answer the following four questions:

1. What is the Total Price? This is what you would charge the customer so that you can have your profit markup of 10% over all of your costs. To calculate this, first figure out your cost per each session, add them up, and then add your profit.

2. What is the Per Session Price? This is the revenue that the customer pays you each time you complete a session. It is calculated by dividing the Total Price by the number of sessions.

3. What is the Break Even Point? At the beginning, your cost per session is more than your revenue per session. As each session is completed, however, your costs for the session declines so that eventually your cumulative revenue exceeds the cumulative cost. The break-even point is the session at which, for the first time, your revenue exceeds your cost.

4. Assume you win the contract and your customer likes the training so much, she orders a ninth course at the same price as the first eight. What will your profit be on the 9th course?

5. If your learning rate was 80%, would your time to produce a second course be more or less than it was at 90%

Question II: You have just been assigned as Project Manager (PM) to the Kuraiz-Reconda Fiber Optic Cable (KRFOC) project. You are preparing your cost estimate for the project and your Project Engineer (PE) tells you it will take 425 hours to complete the design effort. Your Finance Manager (FM) tells you that engineering labor is $125 an hour. Fortunately for you, unfortunately for them, you are a graduate of UMGC, specializing in project management in general and advanced project management techniques in particular.

Upon questioning, your PE admits that the 425 hours is just a guess, that under the best circumstances, meaning you quit bugging him with inane questions, it may take only 375 hours. However, it could take as long as 700 hours (if you do not leave him alone to do his job). He stands by his estimate that it will normally take 425 hours. Hint: this is a triangular distribution.

Thinking back to your UMGC days, you wonder if all engineers cost $125 per hour. Upon questioning, your FM admits that this is an average cost, that the highest salary is $150, the lowest is $100. You direct him to give you the distribution of all engineer labor rates. With a lot of help (your FM does not have the benefit of your UMGC education), he replies that the labor rate is uniformly distributed.

Answer the following two questions:

1. Using this information and a wonderful tool you mastered at UMGC, Crystal Ball (CB), what is the mean cost of your engineering effort?

2. You are about to present your cost estimate to your sponsor when you remember that he was once a Professor at UMGC. You recall, too, that he wore both a belt and suspenders and you suspect that this meant he might be a bit conservative. You therefore decide to provide an engineering cost estimate such that you are confident that 95% of the time your actual costs would be less than that value and that no more than 5% of the time would you exceed that value. What is your new estimate of engineering costs?

3. You present your cost estimate to your sponsor. He rejects it as way, way too high. He asks what you intend to do about it. Do you:

a. Fire your engineer.
b. Write your PMAN 635 Professor and ask him where you went wrong (after all, you got a D+ in his course).
c. Request the sponsor give you another probability that he is comfortable with and re-run the estimate of costs.

Format your homework according to the give formatting requirements:

1. The answer must be double spaced, typed, using Times New Roman font (size 12), with one-inch margins on all sides.

2. The response also includes a cover page containing the title of the homework, the course title, the student's name, and the date. The cover page is not included in the required page length.

3. Also include a reference page. The references and Citations should follow APA format. The reference page is not included in the required page length.

Request for Solution File

Ask an Expert for Answer!!
Project Management: What is the total price
Reference No:- TGS03074559

Expected delivery within 24 Hours