What is the rationale behind the npv method


Case Scenario: Allied Components Company

You recently went to work for Allied Components Company, a supplier of auto repair parts used in the after-market with products from DaimlerChrysler, Ford, and other auto makers. Your boss, the chief financial officer (CFO), has just handed you the estimated cash flows for two proposed projects. Project L involves adding a new item to the firm's ignition system line; it would take some time to build up the market for this product, so the cash inflows would increase over time. Project S involves an add-on to an existing line, and its cash flows would decrease over time. Both projects have 3-year lives, because Allied is planning to introduce entirely new models after 3 years.

Here are the projects' net cash flows (in thousands of dollars):

Year                 0        1        2       3
Project L     —$100    $10    $60    $80
Project S     —$100    $70    $50    $20

Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows.

The CFO also made subjective risk assessments of each project, and he concluded that both projects have risk characteristics that are similar to the firm's average project. Allied's WACC is 10 percent. You must now deter¬mine whether one or both of the projects should be accepted.

A) What is capital budgeting? Are there any similarities between a firm's capital budgeting decisions and an individual's investment decisions?

B) What is the difference between independent and mutually exclusive projects? Between projects with normal and nonnormal cash flows?

C1) Define the term net present value (NPV). What is each project's NPV?

C2) What is the rationale behind the NPV method? According to NPV, which project or projects should be accepted if they are independent? Mutually exclusive?

C3) Would the NPVs change if the WACC changed?

D1) Define the term internal rate of return (IRR). DO NOT calculate

D2) How is the IRR on a project related to the YTM on a bond?

E1) What is the payback period? Find the paybacks for Projects L and S.

E2) What is the rationale for the payback method? According to the payback criterion, which project or projects should be accepted if the firm's maximum acceptable payback is 2 years, and if Projects L and S are independent?

If they are mutually exclusive?

E3) What is the difference between the regular and discounted payback methods?

E4) What are the two main disadvantages of discounted payback? Is the payback method of any real usefulness in capital budgeting decisions?
 
F) As a separate project (Project P), the firm is considering sponsoring a pavilion at the upcoming World's Fair. The pavilion would cost $800,000, and it is expected to result in $5 million of incremental cash inflows during its 1 year of operation. However, it would then take another year, and $5 million of costs, to demolish the site and return it to its original condition. Thus, Project P's expected net cash flows look like this (in millions of dollars):

Time                 0         1            2   
Cash Flows    —$0.8    $5.0    —$5.0

The project is estimated to be of average risk, so its WACC is 10 percent.

F1)  What is Project P's NPV?

F2)  Does Project P have normal or nonnormal cash flows?

Should this project be accepted? Explain.

Solution Preview :

Prepared by a verified Expert
Finance Basics: What is the rationale behind the npv method
Reference No:- TGS02048430

Now Priced at $30 (50% Discount)

Recommended (98%)

Rated (4.3/5)