What is the projects apv


Problem: A project cost $1 million and has a base-case NPV of exactly zero (NPV = 0). What is the projects' APV in the following cases?

a. If the firm invests, it has to raise $500,000 by a stock issue. Issue costs are 15% of net proceeds.

b. If the firm invests, its debt capacity increases by $500,000. The present value of interest tax shield on this debt is $76,000.

Solution Preview :

Prepared by a verified Expert