What is the optimal production schedule


Assignment:

Q: The Textile Mill produces five different fabrics. Each fabric can be woven on one or more of the mill's 38 looms. The sales department's forecast of demand for the next month is shown below, along with data on the selling price per yard, variable cost per yard, and purchase price per yard. The mill operates 24 hours a day and is scheduled for 30 days during the coming month.

Fabric

Demand (yards)

Selling price ($/yard)

Variable Cost ($/yard)

Purchase Price ($/yard)

1

16,500

0.99

0.66

0.80

2

22,000

0.86

0.55

0.70

3

62,000

1.10

0.49

0.60

4

7,500

1.24

0.51

0.70

5

62,000

0.70

0.50

0.70

The mill has two types of looms: dobbie and regular. The dobbie looms are more versatile and can be used for all five fabrics. The regular looms can produce only three of the fabrics. The mill has a total of 38 looms: 8 are dobbie and 30 are regular. The rate of production for each fabric on each type of loom is given in the following table. The time required to change over from producing one fabric to another is negligible and does not have to be considered.


Loom Rate (yards/hour)

Fabric

Dobbie

Regular

1

4.63

-

2

4.63

-

3

5.23

5.23

4

5.23

5.23

5

4.17

4.17

The Textile Mill satisfies all demand with either its own fabric or fabric purchased from another mill. Fabrics that cannot be woven at the Scottsville Mill because of limited loom capacity will be purchased from another mill. We use following linear programming model to maximize the profit of the Textile Mill and to answer the management's questions:

Let                X3R = Yards of fabric 3 on regular looms

                     X4R = Yards of fabric 4 on regular looms

                     X5R = Yards of fabric 5 on regular looms

                     X1D = Yards of fabric 1 on dobbie looms

                     X2D = Yards of fabric 2 on dobbie looms

                     X3D = Yards of fabric 3 on dobbie looms

                     X4D = Yards of fabric 4 on dobbie looms

                     X5D = Yards of fabric 5 on dobbie looms

                     Y1   = Yards of fabric 1 purchased

                     Y2   = Yards of fabric 2 purchased

                     Y3   = Yards of fabric 3 purchased

                     Y4   = Yards of fabric 4 purchased

                     Y5   = Yards of fabric 5 purchased

Max 0.61X3R + 0.73X4R + 0.20X5R + 0.33X1D + 0.31X2D + 0.61X3D + 0.73X4D + 0.20X5D + 0.19Y1 + 0.16Y2 + 0.50Y3 + 0.54Y4

Subject to:

0.1912X3R + 0.1912X4R + 0.2398X5R £ 21600 (Regular Hours Available)

0.21598X1D + 0.21598X2D + 0.1912X3D + 0.1912X4D + 0.2398X5D £ 5760 (Dobbie Hrs Available)

      X1D + Y1

= 16500


          X2D + Y2

= 22000   (Demand Constraints)            


X3R + X3D + Y3

= 62000


X4R + X4D + Y4

= 7500


X5R + X5D + Y5

= 62000


ALL variables >=0

OPTIMAL SOLUTION OBTAINED WITH LINGO:

a) What is the optimal production schedule and loom assignments for each fabric?

Optimal Objective Value


62531.49090






Variable

Value

Reduced Cost

X3R

27707.80815

0.00000

X4R

7500.00000

0.00000

X5R

62000.00000

0.00000

X1D

4668.80000

0.00000

X2D

22000.00000

0.00000

X3D

0.00000

-0.01394

X4D

0.00000

-0.01394

X5D

0.00000

-0.01748

Y1

11831.20000

0.00000

Y2

0.00000

-0.01000

Y3

34292.19185

0.00000

Y4

0.00000

-0.08000

Y5

0.00000

-0.06204




Constraint

Slack/Surplus

Dual Value

1

0.00000

0.57530

2

0.00000

0.64820

3

0.00000

0.19000

4

0.00000

0.17000

5

0.00000

0.50000

6

0.00000

0.62000

7

0.00000

0.06204







Objective

Allowable

Allowable

Coefficient

Increase

Decrease

0.61000

0.01394

0.11000

0.73000

Infinite

0.01394

0.20000

Infinite

0.01748

0.33000

0.01000

0.01575

0.31000

Infinite

0.01000

0.61000

0.01394

Infinite

0.73000

0.01394

Infinite

0.20000

0.01748

Infinite

0.19000

0.01575

0.01000

0.16000

0.01000

Infinite

0.50000

0.11000

0.01394

0.54000

0.08000

Infinite

0.00000

0.06204

Infinite




RHS

Allowable

Allowable

Value

Increase

Decrease

21600.00000

6556.82444

5297.86007

5760.00000

2555.33477

1008.38013

16500.00000

Infinite

11831.20000

22000.00000

4668.80000

11831.20000

62000.00000

Infinite

34292.19185

7500.00000

27707.80815

7500.00000

62000.00000

22092.07648

27341.95794

1 dobbie loom for fabric one, 6 dobbie looms for fabric two, 7 regular looms for fabric 3, 2 regular looms for fabric four, 20 regular looms for fabric 5 the whole time (one month); one doobie looms for fabric 1 for 4/10 of month and the rest of the time used for fabric two; one regular loom to make fabric 3 for 4/10 month and to make fabric 5 the rest of the month

b) How many yards of each fabric must be purchased from another mill?

Fabric 1 - 11813.2 purchased from another mill

Fabric 2 - none

Fabric 3 - 34,292.18 purchased from somewhere else

Fabric 4 - none

Fabric 5 - none

c) What is the maximum profit attainable with the suggested production schedule?

The profit would be $62,531.48

d) If the purchase price of fabric 3 is decreased by $0.10, would the optimal solution change?

e) If the mill increased the selling price of fabric 2 on dobbie looms to $1.00, would the production schedule change? How much profit change would you expect?

f) How much is it worth for the company to have an extra regular hour available?

g) How much is it worth for the company to have an extra dobbie hour available?

An extra doomie loom would be best to be used to make fabric 1 all month and an additional profit of $466.70 and 3333.6 yard of fabric one would be produced. This is because fabric 1 and 3 are being brought more expense than to produce them.

h) What is the maximum value of the 9th Dobbie Loom;­ i.e., how much they should be willing to pay for the additional dobbie loom?

i) Management would like to understand the effects of different demand levels for different fabrics on the optimal solution and the total profit. Discuss the range of feasibility and the value of extra demand for each fabric.

j) If the company has to choose only one fabric to promote by additional advertisement, which fabric they should choose and why?

k) If they increase the selling price for fabric 1 and 4 by $0.10 simultaneously, would the optimal solution change? What would be the optimal total cost?

l) After implementing lean strategies, they plan to increase available regular hours to 25000 and available dobbie hours to 4000. Will there be any savings or total cost increase?

Request for Solution File

Ask an Expert for Answer!!
Operation Research: What is the optimal production schedule
Reference No:- TGS02056726

Expected delivery within 24 Hours