What is the new critical path and earliest completion time


The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, time & sequence required:

Activity Immediate predecessor Time (weeks)
A --- 3
B A 2
C A 4
D A 4
E B 6
F C,D 6
G D,F 2
H D 3
I E,G,H 3

A.) What is the critical path?
B.) Suppose you want to shorten the completion time as much as possible, & you have the option of shortening any or all of B,C,D, and G each one week. Which would you shorten?
C.) What is the new critical path & earliest completion time?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the new critical path and earliest completion time
Reference No:- TGS090777

Expected delivery within 24 Hours