What is the net present value npv of the project if the


A project has an initial outlay of $4,098. It has a single payoff at the end of year 9 of $6,162. What is the net present value (NPV) of the project if the company’s cost of capital is 9.41 percent?

Round the answer to two decimal places.

Request for Solution File

Ask an Expert for Answer!!
Financial Management: What is the net present value npv of the project if the
Reference No:- TGS02332851

Expected delivery within 24 Hours