What is the irr for each of these projects using the irr


1. Garage, Inc., has identified the following two mutually exclusive projects:

Year Cash Flow (A)
Cash Flow (B)
0 -$ 29,400

-$ 29,400
1
14,800


4,500
2
12,700


10,000
3
9,400


15,600
4
5,300


17,200

a-1  What is the IRR for each of these projects? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.

IRR
Project A %
Project B %

a-2  Using the IRR decision rule, which project should the company accept?

Project A
Project B

a-3 Is this decision necessarily correct?
Yes
No

b-1 If the required return is 12 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

NPV
Project A $
Project B $

b-2 Which project will the company choose if it applies the NPV decision rule?
Project A
Project B

c.  At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations. Enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

Discount rate %

2.The Sloan Corporation is trying to choose between the following two mutually exclusive design projects.

Year Cash Flow
(I)

Cash Flow
(II)
0 -$ 63,000

-$ 18,100
1
32,000


9,750
2
32,000


9,750
3
32,000


9,750

a-1  If the required return is 11 percent, what is the profitability index for both projects? (Do not round intermediate calculations. Round your answers to 3 decimal places, e.g., 32.161.)

Profitability
Index
Project I
Project II

a-2 If the company applies the profitability index decision rule, which project should the firm accept?

Project I
Project Il

b-1  What is the NPV for both projects? (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

NPV
Project I $
Project II $

b-2  If the company applies the NPV decision rule, which project should it take?

Project I
Project II

3. Consider the following two mutually exclusive projects:

Year Cash Flow
(A)

Cash Flow
(B)
0 -$ 342,000
-$ 50,500
1
53,000

24,800
2
73,000

22,800
3
73,000

20,300
4
448,000

15,400

Whichever project you choose, if any, you require a 14 percent return on your investment.

a-1  What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

Payback period
Project A years
Project B years

a-2 If you apply the payback criterion, which investment will you choose?
Project A
Project B

b-1  What is the discounted payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

Discounted payback period
Project A years
Project B years

b-2 If you apply the discounted payback criterion, which investment will you choose?
Project A
Project B

c-1  What is the NPV for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)

NPV
Project A $
Project B $

c-2 If you apply the NPV criterion, which investment will you choose?
Project A
Project B

d-1  What is the IRR for each project? (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)

IRR
Project A %
Project B %

d-2 If you apply the IRR criterion, which investment will you choose?
Project A
Project B

e-1 What is the profitability index for each project? (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.)

Profitability index
Project A
Project B

e-2 If you apply the profitability index criterion, which investment will you choose?
Project A
Project B
f. Based on your answers in (a) through (e), which project will you finally choose?
(Click to select)Project AProject B

please answer all parts of all questions, thank you much appreciated

Request for Solution File

Ask an Expert for Answer!!
Financial Management: What is the irr for each of these projects using the irr
Reference No:- TGS02698700

Expected delivery within 24 Hours