What is budgeted indirect cost allocation rate for activity


1.The allocation of indirect costs in an activity-based costing system

  • may require other costs to be allocated to activities before the costs of the activities can be allocated to the products.
  • is simplified because more costs are identified as direct costs.
  • requires the use of heterogeneous cost pools.
  • is simplified because a limited number of activities are identified as cost objects.

2.The MOST likely example of an output unit-level cost is

  • general administrative costs.
  • paying suppliers for orders received.
  • engineering costs.
  • machine depreciation.

3.Different products consume different proportions of manufacturing overhead costs because of differences in all of the following EXCEPT

  • selling prices.
  • customers' customization specifications.
  • setup times.
  • product design.

4.A PRIMARY reason for assigning selling and distribution costs to products for analytical purposes is

  • to justify a product mix.
  • that controllers are required to assign all costs when valuing inventories.
  • that different processes, products, and customers require different quantities of selling and distribution activities.
  • that all indirect costs must be assigned.

5.Products make diverse demands on resources because of differences in all of the following EXCEPT

  • volume.
  • selling price.
  • batch size.
  • complexity.

6.Dalrymple Company produces a special spray nozzle. The budgeted indirect total cost of inserting the spray nozzle is $80,000. The budgeted number of nozzles to be inserted is 40,000. What is the budgeted indirect cost allocation rate for this activity?

  • $0.50
  • $1.00
  • $1.50
  • $2.00

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What is budgeted indirect cost allocation rate for activity
Reference No:- TGS0707832

Expected delivery within 24 Hours