What are the projects true npv


Problem:

Project C0    C1    C2    C3    C4    C5    Etc.    IRR (%)    NPV at 10%
F    -9000    6000    5000    4000    0    0    ...    33    3592
G    -9000    1800    1800    1800    1800    1800    ...    20    9000
H    -6000    1200    1200    1200    1200    ...    20    6000

Look back to the cash flows for projects F and G in Section 5-3, the cost of capital was assumed to be 10%. Assume that the forecasted cash flows for projects of this type are overstated by 8% on average. That is, the forecast for each cash flow from each project should be reduced by 8%. But a lazy financial manager, unwilling to take the time to argue with the projects' sponsors, instructs them to use a discount rate of 18%.

Q1. What are the projects' true NPVs?

Q2. What are the NPVs at the 18% discount rate?

Q3. Are there any circumstances in which the 18% discount rate would give the correct NPV?

Solution Preview :

Prepared by a verified Expert
Finance Basics: What are the projects true npv
Reference No:- TGS01810596

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)