What amounts should be recorded as the initial values of


During 2016, Burr Co. made the following expenditures related to the acquisition of land and the construction of a building:

Purchase price of land

$

60,000

  Legal fees for contracts to purchase land

 

2,000

  Architects’ fees

 

8,000

  Demolition of old building on site

 

5,000

  Sale of scrap from old building

 

3,000

  Construction cost of new building (fully completed)

 

350,000

What amounts should be recorded as the initial values of the land and the building?

    Land        

            Building

 
     

$64,000

   $358,000  

$65,000

   $362,000  

$60,000

   $360,000  

$62,000

   $360,000