Use the following information from the arkade company for


Use the following information from the Arkade Company for Problems 5-10

Work Element Mean Observed Time (minutes) Performance Rating Factor

1 1.20 0.95

2 1.00 0.85

3 0.80 1.10

4 0.90 1.10

Calculate the normal time for each of the work elements.