The staff of porter manufacturing has estimated the


Directions: Answer the following questions on a separate document. Explain how you reached the answer or show your work if a mathematical calculation is needed, or both. Submit your assignment using the assignment link in the course shell. This homework assignment is worth 100 points.

Use the following information for Questions 1 through 3: Assume you are presented with the following mutually exclusive investments whose expected net cash flows are as follows:

EXPECTED NET CASH FLOWS:

Year                       Project A                             Project B

0                              -$400                                    -$650

1                              -528                                      210

2                              -219                                      210

3                              -150                                      210

4                              1,100                                     210

5                              820                                         210

6                              990                                         210

7                              -325                                      210

1. (a) What is each project's IRR? (b) If each project's cost of capital were 10%, which project, if either, should be selected? If the cost of capital were 17%, what would be the proper choice?

2. a) What is each project's MIRR at the cost of capital of 10%? At 17%? (Hint: Consider Period 7 as the end of Project B's life.)

3. What is the crossover rate, and what is its significance?

Use the following information for Question 4:

The staff of Porter Manufacturing has estimated the following net after-tax cash flows and probabilities for a new manufacturing process:

Line 0 gives the cost of the process, Lines 1 through 5 give operating cash flows, and Line 5* contains the estimated salvage values. Porter's cost of capital for an average-risk project is 10%.

Net After-Tax Cash Flows

Year                       P = 0.2                   P = 0.6                   P = 0.2

0                              -$100,000            -$100,000            -$100,000

1                              20,000                   30,000                   40,000

2                              20,000                   30,000                   40,000

3                              20,000                   30,000                   40,000

4                              20,000                   30,000                   40,000

5                              20,000                   30,000                   40,000  

5*                           0                              20,000                   30,000

4. Assume that the project has average risk. Find the project's expected NPV. (Hint: Use expected values for the net cash flow in each year.)

Solution Preview :

Prepared by a verified Expert
Finance Basics: The staff of porter manufacturing has estimated the
Reference No:- TGS01414840

Now Priced at $20 (50% Discount)

Recommended (98%)

Rated (4.3/5)