Question 1.1. This plan lays out a strategy for moving from the old system to the new.

Systems service request

Installation plan

Training plan

Testing plan

Conversion guide

Question 2.2. The process of bringing together all of the modules that comprise a program for testing purposes is referred to as
unity testing.

integration testing.

system testing.

implementation.

stub testing.

Question 3.3.  The purpose of acceptance testing is to

determine if new requirements must be added to the newly completed system.

determine if the system meets user requirements.

determine if the system meets its objectives.

test a completed information system using simulated data.

test a completed information system using real data.

Question 4.4. Changing over from the old information system to a new one by turning off the old system as the new one is turned on best describes

phased installation.

single location installation.

parallel installation.

direct installation.

rotation installation.

Question 5.5.  Written or other visual information about an application system, how it works, and how to use it best defines

system documentation.

user documentation.

internal documentation.

external documentation.

application documentation.

Question 6.6.  Which of the following consists of an exhaustive list of the system's functions and commands, usually in alphabetical order?
Reference guide]

User's guide

Release description

System administrator's guide

Programmer's guide

Question 7.7.  Changes made to a system to evolve its functionality to changing business needs or technologies is referred to as

corrective maintenance.

adaptive maintenance.

preventive maintenance.

perfective maintenance.

environmental maintenance.

Question 8.8.  Which of the following influences most of the costs associated with maintaining a system?

Maintenance personnel

Documentation quality

Number of latent defects

Number of customers

Tools

Question 9.9.  An overall test plan is developed during

systems implementation.

systems analysis.

logical design.

physical design.

systems planning and selection.

Question 10.10.  Tests performed during alpha testing that are designed to try to break the system are

stress tests.

performance tests.

recovery tests.

security tests.

stub tests.