The original project hurdle rate was 1050 and the current


Your firm is half-way through a six year project with the following forecast and actual cash flows:

Original Forecast Cash Flows

CF1 = 3.40 million

CF2 = 2.90 million

CF3 = 3.10 million

CF4 = 2.95 million

CF5 = 3.25 million

CF6 = 3.00 million

Actual Cash Flows to Date

CF1 = 3.20 million

CF2 = 2.75 million

CF3 = 3.00 million

The original forecasted project investment was $10 million, but the actual investment was $12 million. The original project hurdle rate was 10.50% and the current hurdle rate is 11.50%. What is the revised net present value of this project? Please show calculations.

a) 351,404

b) 559,254

c) 709,143

d) None of the above

Request for Solution File

Ask an Expert for Answer!!
Financial Management: The original project hurdle rate was 1050 and the current
Reference No:- TGS02826462

Expected delivery within 24 Hours