The management likes to have operators working 90 of the


The Universal Manufacturing Company produces a particular product in an assembly line operation. One of the machines on the line is a drill press that has a single assembly line feeding into it. A partially completed unit arrives at the press to be worked on every 8 minutes, on average, according to an exponential distribution. The machine operator can process an average of 10 parts per hour (Poisson distributed).


Determine the average number of parts waiting to be worked on.
Determine the percentage of time the operator is working.
Determine the percentage of time the machine is idle.
The management likes to have operators working 90% of the time. What must the assembly line arrival rate be in order for the operators to be as busy as management would like?

 

Request for Solution File

Ask an Expert for Answer!!
Operation Management: The management likes to have operators working 90 of the
Reference No:- TGS0571366

Expected delivery within 24 Hours