The cost actually incurred and recorded in accomplishing


1: The cost actually incurred and recorded in accomplishing the work within a given time period is called the: (a)Cost Variance. (b)Budget at Completion (c)Actual Cost of work performed (d)Budgeted Cost for work performed

2: To trigger a formal schedule or cost performance analysis, the program office establishes: (a)Variance thresholds (b)Scheduled review points (c)End of contract assessments (d)Periodic depending on performence achevement

3: The most important and critical part of earned value is: (a)The accurate determination of the actual cost of the work performed (b)A realistic approach to work package planning and BCWS values for milestones (c)The use of a computerized system collecting data and calculating performance (d) The determination of cost performance compared to the originally developed plans

4:  _____ is responsible for evaluating the reasonableness of the offered prices. (a)Contracting officer (b)Price analyst (c)Engineer (d)Contract auditor (e)None of the above

5: Cost estimates are submitted by contractors in connection with: (a)Modification and change proposals (b)Prices of spare parts (c)Rates for time and material contracts (d) estimated and final costs of cost type contracts (e) All of the above

Request for Solution File

Ask an Expert for Answer!!
Financial Management: The cost actually incurred and recorded in accomplishing
Reference No:- TGS01558857

Expected delivery within 24 Hours