The company uses machine hours as its overhead allocation


Question - A company estimates $10M in direct labor and overhead costs for the next year will be $7,500,000 for indirect labor and $650,000 for factory utilities. The company uses machine hours as its overhead allocation base. If 250,000 machine hours are planned for this next year, what is the company's plantwide overhead rate?

A. $.0306 per machine hour.

B. $32.60 per machine hour.

C. $30.00 per machine hour.

D. $2.600 per machine hour.

E. $.0137 per machine hour.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: The company uses machine hours as its overhead allocation
Reference No:- TGS02876994

Now Priced at $20 (50% Discount)

Recommended (92%)

Rated (4.4/5)