Module 5: Problem 1. 
 The board of directors of Ogle Construction Company is meeting to choose  between the completed-contract method and the percentage-of-completion  method of accounting for long-term contracts in the company's financial  statements. You have been engaged to assist Ogle's controller in the  preparation of a presentation to be given at the board meeting. The  controller provides you with the following information:
 1.	Ogle commenced doing business on January 1, 2013.
 2.	Construction activities for the year ended December 31, 2013, were as follows:
 
 Total Contract	Billings Through	Cash Collections
 Project	Price	12/31/13	Through 12/31/11
 A	$   510,000	 $  340,000	$   310,000
 B	     700,000	     210,000	     210,000
 C	     475,000	     475,000	     390,000
 D	     200,000	     100,000	       65,000
 E	     460,000	     400,000	     400,000
 $2,345,000	$1,525,000	$1,375,000
 
 Contract Costs	Estimated
 Incurred Through	Additional Costs to
 Project	12/31/13	Complete Contracts
 A	$   424,000	$101,000
 B	     195,000	  455,000
 C	     350,000	-0-
 D	     123,000	    97,000
 E	     320,000	    80,000
 $1,412,000	$733,000
 
 3.	Each contract is with a different customer.
 4.	Any work remaining to be done on the contracts is expected to be completed in 2014.
 
 Instructions
 (a)	Prepare a schedule by project, computing the amount of income (or  loss) before selling, general, and administrative expenses for the year  ended December 31, 2013, which would be reported under:
 (1)	The completed-contract method.
 (2)	The percentage-of-completion method (based on estimated costs).
 (b)	Prepare the general journal entry(ies) to record revenue and gross  profit on project B (second project) for 2013, assuming that the  percentage-of-completion method is used.
 (c)	Indicate the balances that would appear in the balance sheet at  December 31, 2013 for the following accounts for Project D (fourth  project), assuming that the percentage-of-completion method is used.
 Accounts Receivable
 Billings on Construction in Process
 Construction in Process
 (d)	How would the balances in the accounts discussed in part (c) change  (if at all) for Project D (fourth project), if the completed-contract  method is used?