The data table below provides cost overruns actual costs


Confidence interval

The data table below provides cost overruns (actual costs minus estimated costs) in thousands of dollars on similar-size engineering projects completed this year. Calculate the following:

a.    A 95 percent confidence interval for the average overrun this process would deliver over a long time period, assuming it is stable.

a.     A 99 percent confidence interval for the same average.

Explain why this is a different width than the 95 percent interval.

  -16

-480

-222

-404

  -77

  -76

-397

 221

-427

 113

  93

-268

-791

 107

-230

-165

-272

  287

-118

 133

-285

    9

 276

-344

-651

  36

-394

 383

-298

 161

Solution Preview :

Prepared by a verified Expert
Mathematics: The data table below provides cost overruns actual costs
Reference No:- TGS01471181

Now Priced at $30 (50% Discount)

Recommended (99%)

Rated (4.3/5)