Ted company had incurred overhead of 216000 and had


Problem - Bill Company and ted company both use predetermined overhead rates to apply manufacturing overhead to production. Bill's is based on machine hours and Ted's is based materials cost. Budgeted production and cost data for Bill and Ted are as follows:

Bill Ted

Manufacturing overhead $304,000 $220,000

Units 10,000 20,000

Machine hours 16,000 9,700

Materials cost 155,000 400,000

At the end of the year, Bill company had incurred overhead of $305,000 and had produced 9,800 units using 15,900 machine hours and materials costing $152,000. Ted company had incurred overhead of $216,000 and had produced 20,500 units using 9,750 machine hours and materials costing $395,000

1. Compute the predetermined overhead rates for Bill and Ted?

2. Was overhead over or under applied for each company, and by how much?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Ted company had incurred overhead of 216000 and had
Reference No:- TGS02570529

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)