Suppose the projections given for price quantity variable


We are evaluating a project that costs $1,422,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 88,200 units per year. Price per unit is $34.85, variable cost per unit is $21.10, and fixed costs are $762,000 per year. The tax rate is 35 percent, and we require a return of 11 percent on this project.

Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent. Calculate the best-case and worst-case NPV figures. (A negative answer should be indicated by a minus sign. Enter your answers in dollars, not millions of dollars, e.g. 1,234,567. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)