Suppose that a feasibility study done for a project by a


Suppose that a feasibility study done for a project by a consulting company brought the following results: 

PW (Benefits) = $13 million

PW (Costs) = $10 million

It was mentioned in the feasibility study that there is a risk of the project's loss due to potential high inflation. How should the project manager react to these results?

Question options:

1) Terminate the project at initiation stage

2) Proceed with the project to the planning stage during which the risk of inflation should be addressed

3) Terminate the project right away

4) Use Monte Carlo simulation to address the risk

5) Look for a second opinion on feasibility study