Single plant-wide factory overhead rate


Problem 1. Using activity-based systems, the stage of the management cycle that identifies actions that will reduce the full product or service cost is:

a. planning.

b. executing.

c. reviewing.

d. reporting.

Problem 2. Lasso Corp. budgeted $250,000 of overhead cost for 2001. Actual overhead costs for the year were $240,000. Lasso's plant-wide allocation base, machine hours, was budgeted at 50,000 hours. Actual machine hours were 40,000. Budgeted units to be produced are 100,000 units. Lasso's plant-wide factory overhead rate for 2001 is:

a. $1.25 per unit

b. $6.00 per machine hour

c. $6.25 per machine hour

d. $5.00 per machine hour

Problem 3. Hoskins Co. uses a plant-wide factory overhead rate based on direct labor hours. Overhead costs would be overcharged to which of the following departments?

a. A labor-intensive department.

b. A capital-intensive department.

c. A material-intensive department.

d. None of the above.

Problem 4. Using multiple department factory overhead rates instead of a single plant-wide factory overhead rate:

a. results in more accurate product costs.

b. results in distorted product costs.

c. is simpler and less costly.

d. applies overhead costs to all departments equally.

Problem 5. Using a plant-wide factory overhead rate distorts product cost when:

a. products require different ratios of allocation-base usage in each production department.

b. significant differences exist in the factory overhead rates used across different production departments.

c. both A and B exist

d. either A or B exist

Problem 6. Zinn Co. uses 3 machine hours and 1 direct labor hour to Produce Product X. It uses 4 machine hours and 8 direct labor hours to produce Product Y. Zinn's assembly and finishing Departments have factory overhead rates of $240 per machine hour and $160 per direct labor hour, respectively. How much overhead cost will be charged to the two products?

a. Product X - $240; Product Y = $160.

b. Product X - $400; Product Y = $400.

c. Product X - $880; Product Y = $2,240.

d. product X - $720; Product Y = $1,280.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Single plant-wide factory overhead rate
Reference No:- TGS01739533

Now Priced at $20 (50% Discount)

Recommended (91%)

Rated (4.3/5)