Shipments of product x from a plant to a wholesaler are


Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. Lead time from plant to wholesaler is 4 weeks. The wholesaler pays for the shipments when they leave the plant. What is the total of the wholesaler's current cycle plus pipeline inventories?