Set up the job cost sheets for job no j57 and job no k52


Q1. ACECO Continuing Problem

ACECO has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain which will require special-order sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December 2012.

Raw materials were requisitioned from the company's inventory on December 2 for $5,061; on December 8 for $1,059; and on December 14 for $3,459. In each instance, two-thirds (2/3) of these materials were for J57 and the rest for K52.

Six time tickets were turned in for these two projects for a total amount of 18 hours of work. All the workers were paid $16.50 per hour. The time tickets were dated December 3, December 9, and December 15. On each of those days, 6 labor hours were spent on these jobs, two-thirds (2/3) for J57 and the rest for K52.

The predetermined overhead rate is based on machine hours. The expected machine hour use for the year is 2,112 hours, and the anticipated overhead costs are $840,576 for the year. The machine were used by workers on projects K52 and J57 on December 3, 9, and 15. Six machine hours were used for project K52 (2 each day), and 8.5 machine hours were used for project J57 (2.5 the first day and 3 each of the other days). Both of these special orders were completed on December 15, producing 237 sprinkler heads for J57 and 142 sprinkler heads for K52.

Additional job order activities during this period of time included:

Dec.  1   Purchased raw materials from Durbin Supply Company on account for $53,200.

Dec.  2   Issued $40,000 of direct materials from the company's inventory to jobs other than K52 and J57 and $3,000 of indirect materials.

Dec.12  Paid ACECO factory salaries and wages in the amount of $65,000.

Dec.13  Paid the factory's water bill of $9,000.

Dec.18  Transferred $50,000 of costs from other completed jobs to finished goods.

Dec.21  Paid the factory's electric bill of $12,000 for ACECO' factory.

Dec.31  Made adjusting entries for the factory that included accrued property taxes of $12,000, prepaid insurance of $8,800, and accumulated depreciation of $16,000.

Instructions

(a) Set up the job cost sheets for Job No. J57 and Job No. K52. Determine the total cost for each manufacturing special order for these jobs. (Round unit cost to nearest cent.)

(b) Journalize the activities from these job cost sheets in the general journal. Also journalize the other costs that occurred during this period of time.

(c) Assuming that Manufacturing Overhead has a debit balance of $3,600, determine whether overhead has been under/over applied and make the adjusting entry.

(d) Why would ACECO choose machine hours as the cost driver for the overhead rather than direct labor cost?

Q2. ACECO Continuing Problem

Because most of the parts for its irrigation systems are standard, ACECO handles the majority of its manufacturing as a process cost system. There are multiple process departments. Three of these departments are the Molding, Cutting, and Welding departments. All items eventually end up in the Package department which prepares items for sale in kits or individually.

The following information is available for the Molding department for January.

Work in process beginning:


    Units in process

22,000

    Stage of completion for materials

80%

    Stage of completion for labor and overhead

30%

Costs in work in process inventory:


         Materials

$168,360

         Labor

67,564

         Overhead

17,270

    Total costs in beginning work in process

$253,194

Units started into production in January

60,000

Units completed and transferred in January

58,000

Costs added to production:


         Materials

$264,940

         Labor

289,468

         Overhead

60,578

Total costs added into production in January

$614,986

Work in process ending:


         Units in process

24,000

         Stage of completion for materials

50%

         Stage of completion for labor and overhead

10%

Instructions

(a) Prepare a Equivalent Units of Production report for ACECO using the weighted-average method.

(b) Prepare a Cost Per Equivalent Unit report for ACECO using the weighted-average method.

(c) Prepare a Costs of Ending Work in Process Inventory and Units Transferred Out report for ACECO using the weighted-average method.

Q3. ACECO Continuing Problem

Direct labor or machine hours may not be the appropriate cost driver for overhead in all areas of manufacturing due to the complexities of many manufacturing processes. Many companies use activity-based costing (ABC) which uses multiple drivers (items that consume resources) rather than just one driver to apply overhead to their activities. With ABC, a company can use a cost driver that has a direct cause/effect relationship in its applied overhead costs.

ACECO looked into ABC as a method of costing because of the variety of items it produces and the many different activities in which it is involved. The activities listed below are a sample of possible cost pools for ACECO.

Assembling

Payroll

Billing

Plant supervision

Digging trenches

Product design

Janitorial

Purchasing materials

Machine maintenance

Selling

Machine setups

Testing

Molding

Welding

Packaging


Instructions

(a) For each of these cost pools, what would be the likely activity cost driver?

(b) Using the following information, determine the overhead rates and the actual cost assigned for each of the activity cost pools in a possible ABC system for ACECO.

ACECO CORPORATION

Activity Cost Pools

Cost Drivers

Estimated Overhead

Expected Use of Cost Drivers per Activity

Actual Use of Drivers

Irrigation installation

Labor cost

$1,998,432

12,960

12,941

Machining (all machine use)

Machine hours

1,670,400

33,408,000

33,409,000

Customer orders

Number of orders

30,636

2,553

2,520

Shipping

none (direct)


N/A

traced directly

Design

Cost per design

820

8

7

Selling

Number of sales calls

350,400

21,900

22,100

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Set up the job cost sheets for job no j57 and job no k52
Reference No:- TGS02380741

Now Priced at $30 (50% Discount)

Recommended (99%)

Rated (4.3/5)