Recalculate the project npv


Problem: After taking into account all of the relevant cash flows from the previous question, the company's CFO has estimated the project's NPV and has also put together the following scenario analysis:

Scenario    Prob. of Scenario Occurring Expected NPV
County taxes increased      25%    $ 5 million
County taxes unchanged    50         8 million
County taxes decreased    25        10 million

On the basis of the numbers calculated above, the CFO estimates that the standard deviation of the project's NPV is 2.06. The company typically calculates a project's coefficient of variation (CV) and uses this information to assess the project's risk. Here is the scale that Bruener uses to evaluate project risk:

Range for Coefficient    Risk    Project's
of Variation (CV) Assessment    WACC

CV > 0.3    High risk    12%
0.2CV < 0.2    Low risk    8

On the basis of this scenario analysis, which of the following statements is most correct?

a) The project's expected NPV is $7.75 million.

b) The project would be classified as an average-risk project.

c) If the project were classified as a high-risk project, the company should go back and recalculate the project's NPV using the higher cost of capital estimate.

d) Statements a and b are correct.

e) All of the statements above are correct.

Solution Preview :

Prepared by a verified Expert
Finance Basics: Recalculate the project npv
Reference No:- TGS01810841

Now Priced at $25 (50% Discount)

Recommended (99%)

Rated (4.3/5)