question 1 a gantt chart represents mainlyanswer


Question 1

A GANTT chart represents mainly

Answer

an immediate identification of predecessor task.

a record-keeping device used in scheduling activities.

a general identifier.

the number of workers directly involved in the project.

Question 2

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
Answer

7.0

7.5

8.0

8.5

Question 3

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
Answer

7/6

1/3

2/3

1.0

Question 4

A list of the tasks, broken down into modules, components, and individual tasks, is called a
Answer

work breakdown structure (WBS).

PERT.

planning matrix.

critical path.

Question 5

A work breakdown structure breaks down a project into
Answer

weeks.

areas.

arcs.

modules.

Question 6

Consider the following project.

 

What is the critical path?
Answer

ACFG

ADFG

BEG

ACDFG

Question 7

Consider the following project.

 

What is the minimum possible time for completing this project?
Answer

15 days

16 days

18 days

20 days

Question 8

Consider the following project.

Compute the slack time for activity C.
Answer

0

4

2

3

Question 9

Consider the following project.

What is the latest possible time that Activity E can be started without delaying the completion of the project?
Answer

8

3

7

9

Question 10

Consider the following project.

What is the latest time that activity B can start without delaying the project?
Answer

0

8

4

7

Question 11

Consider the following project.

What is the latest time that activity B can finish without delaying any other activities?
Answer

0

8

9

4

Question 12

Consider the following project.

Determine the critical path.
Answer

ACEH

BCEH

BDFH

BDGH

Question 13

Consider the following project.

Determine the estimated completion time of the project.
Answer

23 days

22 days

25 days

20 days

Question 14

Consider the following project.

 

Determine the slack for activity D.
Answer

2 days

4 days

6 days

5 days

Question 15

Consider the following project.

Determine the slack for activity F.
Answer

2 days

3 days

4 days

5 days

Question 16

Consider the following project.

How much can activity F be delayed without delaying the project completion?
Answer

1 day

2 days

3 days

4 days

Question 17

Elements of project planning include
Answer

defining project objectives.

identifying activities to crash.

calculating expected times and standard deviations.

conducting a "lessons learned" session.

Question 18

If an activity cannot be delayed without affecting the entire project, then it is a ________ activity.
Answer

completed

critical

crashed

normal

Question 19

If t is the expected completion time for a given activity, then:
Answer

LF = LS - t

EF = ES - t

EF = ES + t

EF = LS - t

Question 20

In a CPM/PERT network the critical path is the
Answer

lowest path through the network.

highest path through the network.

shortest path through the network.

longest path through the network.

Question 21

Joe used a project management software package and has determined the following results for a given project:

What is the probability of completing the project within 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 22

Joe used a project management software package and has determined the following results for a given project.:

What is the probability of completing the project over 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 23


Once a project is underway, the project manager is responsible for the
Answer

people.

cost.

time.

All of these

Question 24


Project control involves
Answer

crashing.

three time estimates.

a backward or forward pass.

earned value analysis.

Question 25

Project management differs from management of more traditional day-to-day activities because
Answer

it has limited time frame.

it has an unlimited budget.

it is more expensive.

it involves more of the workforce.

Question 26

The LS and LF are calculated using the
Answer

backward pass through the network.

forward pass through the network.

values for ES and EF.

backward and forward pass through the network.

Question 27


The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.
Answer

successors

predecessors

successors and predecessors

followers

Question 28

The critical path is the ________ path through the network.
Answer

longest

shortest

straightest

most expensive

Question 29


The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
Answer

$1000

$1250

$2000

$2500

Question 30


Which of these statements regarding project crashing is true?
Answer

Crashing is not possible unless there are multiple critical paths.

Activities not on the critical path cannot become critical after crashing.

Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.

Crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.

Save and Submit

Click Save and Submit to save and submit. Click Save All Answers to save all answers. Click Close Window to close window.

Solution Preview :

Prepared by a verified Expert
Applied Statistics: question 1 a gantt chart represents mainlyanswer
Reference No:- TGS0490658

Now Priced at $40 (50% Discount)

Recommended (96%)

Rated (4.8/5)