Project s costs 15000 and its expected cash flows would be


Project S costs $15,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $37,500, and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Explain.