Project k costs 35000 its expected cash inflows are 12000


Project K costs $35,000, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Project k costs 35000 its expected cash inflows are 12000
Reference No:- TGS01236570