Problem on percentage-of-completion method


Indiana Co. began a construction project in 2006 that will provide it $150 million when it is completed in 2008. During 2006, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project.

In 2007, Indiana incurred costs of $58.5 million and estimated an additional $40.5 million in costs to complete the project. Using the percentage-of-completion method, Indiana:

a) Recognized $15 million gross profit on the project in 2007.

b) Recognized $13.5 million gross profit on the project in 2007.

c) Recognized $6 million gross profit on the project in 2007.

d) Recognized $1.5 million gross profit on the project in 2007.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Problem on percentage-of-completion method
Reference No:- TGS0528253

Expected delivery within 24 Hours