Preparing a job order cost sheet riverwood accounting


Preparing a Job Order Cost Sheet Riverwood Accounting Company has the following account in its cost records:

                                  Work in Process—Jones Audit

Direct labor. . . . . . . . . . . .20,000          Services completed  . . . . . 44,000

Project overhead  . . . . . . .28,000

Riverwood applies overhead to projects at a predetermined rate based on direct labor costs. Assume that Riverwood uses a job order costing system and that Jones Audit is the only job in process at the end of the period. Complete the following cost sheet for services still in process for Jones Audit.

                Job Order Cost Sheet—Jones Audit (Services in Process)

Direct labor. . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Project overhead  . . . . . . . . . . . . . . . . . . . . . . . .

Total cost  . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: Preparing a job order cost sheet riverwood accounting
Reference No:- TGS01603010

Expected delivery within 24 Hours