Prepare the necessary entries for each year


In 2011, Fayette Engineering entered into an agreement to construct an office building at a contract price of $5,100,000. Construction data were as follows:

2011 2012 2013
Construction costs
incurred $ 750,000 $2,700,000 $ 630,000
Estimated costs to
complete 3,000,000 862,500 --
Progress billings 570,000 3,600,000 930,000
Collections from client 450,000 3,300,000 1,350,000

Prepare the necessary entries for each year, assuming the firm uses the:

(1) completed-contract method
(2) percentage-of-completion method.

 

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Prepare the necessary entries for each year
Reference No:- TGS090454

Expected delivery within 24 Hours