Prepare a schedule to compute total gross profit or loss


Long-term contract; revenue recognized over time; loss projected on entire project

Response to the following problem:

Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2016, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2018.

Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows:

 

At 12-31-2016

At 12-31-2017

At 12-31-2018

Percentage of completion

10%

60%

100%

Costs incurred to date

$ 350,000

$2,500,000

$4,250.000

Estimated costs to complete

3,150,000

1,700,000

-0-

Billings to Axelrod, to date

720,000

2,170,000

3,600,000

Required:

1. For each of the three years, prepare a schedule to compute total gross profit or loss to be recognized as a result of this contract.

2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years.

3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2016 and 2017 as either cost in excess of billings or billings in excess of costs.

Solution Preview :

Prepared by a verified Expert
Financial Accounting: Prepare a schedule to compute total gross profit or loss
Reference No:- TGS02092034

Now Priced at $25 (50% Discount)

Recommended (92%)

Rated (4.4/5)