Prepare a manufacturing overhead flexible budget report for


Chubbs Inc.'s manufacturing overhead budget for the first quarter of 2017 contained the following data.

Variable Costs Fixed Costs
Indirect materials $11,300 Supervisory salaries $36,600
Indirect labor 10,600 Depreciation 7,700
Utilities 7,700 Property taxes and insurance 8,000
Maintenance 5,700 Maintenance 5,300

Actual variable costs were indirect materials $15,300, indirect labor $9,300, utilities $9,600, and maintenance $5,100. Actual fixed costs equaled budgeted costs except for property taxes and insurance, which were $9,100. The actual activity level equaled the budgeted level.

All costs are considered controllable by the production department manager except for depreciation, and property taxes and insurance.

(a) Prepare a manufacturing overhead flexible budget report for the first quarter. (List variable costs before fixed costs.)

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Prepare a manufacturing overhead flexible budget report for
Reference No:- TGS02576847