Prepare a diagram showing the required network of tasks and


The Family Planning Research Center of Nigeria

Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria's Over-The-River Province, was assigned the task of organizing and training five teams of field workers as part of a large project to demonstrate acceptance of a new method of birth control. These workers had already had training in family planning education, but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accommodations for the participants.

Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, the necessary sequences, and the time they would require. Their results appear in Table 1.

Table 1 The Family Planning Research Center

 

ACTIVITY

MUST FOLLOW

TIME (IN DAYS)

STAFFING NEEDED

A

Identify faculty and their schedules

--

5

2

B.

Arrange transport to base

--

7

3

C.

Identify and collect training materials

--

5

2

D.

Make accommodations

A

3

1

E.

Identify team

A

7

4

F.

Bring in team

B, E

2

1

G.

Transport faculty to base

A, B

3

2

H.

Print program material

C

10

6

I.

Deliver program materials

H

7

3

J.

Train team

D, F, G, I

15

0

K.

Do fieldwork

J

30

0

Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the times needed given in Table 1. They came to 94 days. "An impossible task then," he noted. "No," Dr. Watage replied, "some of these tasks can go forward in parallel." "Be careful though," warned Mr. Oglagadu, the chief nurse, "there aren't that many of us to go around. There are only 10 of us in this office."

"I can check whether we have enough heads and hands, once I have tentatively scheduled the activities," Dr. Watage responded. "If the schedule is too tight, I have permission from the Pathminder Fund to spend some money to speed it up, just so long as I can prove that it can be done at the least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed times that we planned. Also, here are the costs and times if we shorten them to an absolute minimum." Those data are in Table 2.

Table 2 The Family Planning Research Center

 

 

Normal

Minimum

Average Cost
Per Day Saved ($)

 

Activity

Time

Cost($)

Time

Cost ($)

 

A.

Identify faculty

5

400

2

700

100

B.

Arrange transport

7

1,000

4

1,450

150

C.

Identify materials

5

400

3

500

50

D.

Make accommodations

3

2,500

1

3,000

250

E.

Identify team

7

400

4

850

150

F.

Bring team in

2

1,000

1

2,000

1,000

G.

Transport faculty

3

1,500

2

2,000

500

H.

Print material

10

3,000

6

4,000

250

I.

Deliver materials

7

200

2

600

80

J.

Train team

15

5,000

10

7,000

400

K.

Do fieldwork

30

10,000

20

14,000

400

Source: Professor Curtis P. McLaughlin, Kenan-Flagler Business School, University of North Carolina at Chapel Hill.

Final Project Tasks

  1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required network of tasks, and define the critical path. What is the length of the project without crashing?
  2. At this point, can the project be done given the constraint of having only 10 persons?
  3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve the schedule objective? How can he prove to the Pathminder Fund that this is the minimum cost alternative?
  4. Utilizing the concepts from this course, prepare the project plan based on the information on this case study.  The topics from this class are listed below.  Please incorporate each bullet item into your plan.
  • Define Project Planning
  • Develop the Project Plan
  • Scope Planning
  • Scope Definition
  • Creating the Work Breakdown Schedule (WBS)
  • Activity Definition
  • Activity Sequencing
  • Resource Estimating
  • Duration Estimating
  • Schedule Development and
  • Cost Estimating
  • Cost Budgeting
  • Quality Planning
  • Human Resource Planning
  • Communications Planning
  • Risk Planning and
  • Risk Identification
  • Qualitative Analysis
  • Quantitative Analysis
  • Plan Purchases and Acquisitions
  • Plan Contracting

Solution Preview :

Prepared by a verified Expert
Project Management: Prepare a diagram showing the required network of tasks and
Reference No:- TGS01184050

Now Priced at $70 (50% Discount)

Recommended (98%)

Rated (4.3/5)

A

Anonymous user

4/1/2016 3:47:00 AM

To make an assessment that is about to The Family Planning Research Center of Nigeria Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria's Over-The-River Province, was assigned the task of organizing and training 5 teams of field workers as part of a huge project to show acceptance of a new technique of birth control. Such workers had already had training in family planning education, but must obtain exact training regarding the new process of contraception. Two kinds of substances must as well be arranged: those for employ in training the workers, and those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and adjustments for the participants.