Predecessor activities - those activities that must be


1.Define predecessor, successor, and parallel activities. Give a real world example of each

Predecessor activities - those activities that must be completed before another activity can be started. Ex: Computer's OS must be installed before loading an application package.

Successor activities - activities that must follow a particular activity in some type of sequence. Ex: a program must be tested and then documented after it is compiled.

Parallel activities - an activity or task that can be worked at the same time as another activity. Ex: Design web page layouts and set-up server
 

2. In the context of critical chain project management, what is resource contention?  

3.Define the following and give a real world example of each (other than the ones described in the text book): Finish-to-Start; Start-to-Start; Finish-to-Finish; Start-to-Finish.  

4.     Assume the following activities for a project along with their estimated durations and predecessors. Describe how critical path analysis would be applied to this project, and calculate the critical path. Define the concepts: slack/float, expedite/crash, and fast tracking and explain what their implications are for this project?  

Hint: Start with the following steps:

a.       Draw AON diagram

b.       Calculate Possible Activity paths

c.       Identify critical path

 

Activity

Estimated Duration in Days

Predecessor

A

2

None

B

4

A

C

3

A

D

1

C,B

E

1

C,D

F

3

D,E

G

2

F

Critical Path: A-B-G-F-H

Slack/Float: amount of time an activity can be delayed before it delays the project Expedite/Crash: adding resources to an activity on the critical path to shorten duration Fast Tracking: completing activities in parallel to shorten critical path 

5.     What are the seven IT project risk management processes?  

6.     What is a risk response plan? What should be included? 

7.     Compare the three types of project risk: known, known-unknown, and unknown-unknown. Give an example (not discussed in the text book) of each

8.      Describe the qualities of a good project metric.  

9.       Given the following information, is the Project in trouble?

Calculate: 

a.       Cost Variance (CV) : (CV) = EV AC

b.      Schedule Variance (SV):  (SV) = EV PV

c.       Cost Performance Index  (CPI) : (CPI) = EV/AC

d.      Schedule Performance Index (SPI):  (SPI) = EV/PV 

10.  What are the key differences (4-5) between the Agile Project Management approach and Waterfall (Traditional Project Management) 

11.  What was your favorite topic in this course? 

Request for Solution File

Ask an Expert for Answer!!
Project Management: Predecessor activities - those activities that must be
Reference No:- TGS01186241

Expected delivery within 24 Hours