plot plan alignment generally the process units


Plot Plan Alignment

Generally the process units will be positioned in process flow order, with common utility blocks positioned to provide economical and effective services. Provision is normally made for future expansion without disruption to working units. Administration, storage and loading areas should be located on the periphery.

Elevations of the various units should be determined early to establish a common site datum and relative elevations between units.

A well-designed plant should have a uniform, functional appearance. This document cannot replace the skills of a good Plant Layout Engineer, who through experience will be able to sense whether or not a layout meets the guidelines outlined in this document.