Performing program logic design is activity 12 this can be


Question: Software Development Specialists (SDS) is involved with developing software for customers in the banking industry. SDS breaks a large programming project into teams that perform the necessary steps. Team A is responsible for going from general systems design all the way through to actual systems testing. This involves 18 separate activities. Team B is then responsible for the final installation. To determine cost and time factors, optimistic, most likely, and pessimistic time estimates have been made for all of the 18 activities involved for team A. The first step that this team performs is general systems design. The optimistic, most likely, and pessimistic times are 3, 4, and 5 weeks. Following this, a number of activities can begin. Activity 2 is involved with procedures design. Optimistic, most likely, and pessimistic times for completing this activity are 4, 5, and 12 weeks. Activity 3 is developing detailed report designs. Optimistic, most likely, and pessimistic time estimates are 6, 8, and 10 weeks. Activity 4, detailed forms design, has optimistic, most likely, and pessimistic time estimates of 2, 5, and 5 weeks.

Activities 5 and 6 involve writing detailed program specifications and developing file specifications. The three time estimates for activity 5 are 6, 7, and 8 weeks, and the three time estimates for activity 6 are 3, 4, and 5 weeks. Activity 7 involves specifying system test data. Before this is done, activity 6, involving file specifications, must be completed. The time estimates for activity 7 are 2, 3, and 7 weeks. Activity 8 involves reviewing forms. Before activity 8 can be conducted, detailed forms design must be completed. The time estimates for activity 8 are 3, 3, and 9 weeks. The next activity, activity 9, is reviewing the detailed report design. This requires that the detailed report design, activity 3, be completed first. The time estimates for activity 9 are 1, 3, and 5 weeks, respectively. Activity 10 involves reviewing procedures design. Time estimates are 1, 2, and 9 weeks. Of course, procedures design must be done before activity 10 can be started. Activity 11 involves the system design checkpoint review. A number of activities must be completed before this is done. These activities include reviewing the forms, reviewing the detailed report design, reviewing the procedures design, writing detailed program specs, and specifying system test data. The optimistic, most likely, and pessimistic time estimates for activity 11 are 3, 4, and 5 weeks. Performing program logic design is activity 12. This can be started only after the system design checkpoint review is completed. The time estimates for activity 12 are 4, 5, and 6 weeks.

Activity 13, coding the programs, is done only after the program logic design is completed. The time estimates for this activity are 6, 10, and 14 weeks. Activity 14 is involved in developing test programs. Activity 13 is the immediate predecessor. Time estimates for activity 14 are 3, 4, and 11 weeks. Developing a system test plan is activity 15. A number of activities must be completed before activity 15 can be started. These activities include specifying system test data, writing detailed program specifications, and reviewing procedure designs, the detailed report design, and forms. The time estimates for activity 15 are 3, 4, and 5 weeks. Activity 16, creating system test data, has time estimates of 2, 4, and 6 weeks. Activity 15 must be done before activity 16 can be started. Activity 17 is reviewing program test results. The immediate predecessor to activity 17 is to test the programs (activity 14). The three time estimates for activity 17 are 2, 3, and 4 weeks. The final activity is conducting system tests. This is activity 18. Before activity 18 can be started, activities 16 and 17 must be complete. The three time estimates for conducting these system tests are 2, 6, and 7 weeks. How long will it take for team A to complete its programming assignment?

Request for Solution File

Ask an Expert for Answer!!
Dissertation: Performing program logic design is activity 12 this can be
Reference No:- TGS02724999

Expected delivery within 24 Hours