Percentage-of-completion method


Question: Indiana Co. began a construction project in 2011 that will provide it $165 million when it is completed in 2013. During 2011, Indiana incurred $32 million of costs and estimates an additional $87 million of costs to complete the project. (Do not round your percentage calculated.)

Using the percentage-of-completion method, Indiana:

a. Recognized $78.00 million loss on the project in 2011.

b. Recognized no gross profit or loss on the project in 2011.

c. Recognized $32.00 million loss on the project in 2011.

d. Recognized $12.37 million gross profit on the project in 2011.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Percentage-of-completion method
Reference No:- TGS01894624

Now Priced at $20 (50% Discount)

Recommended (92%)

Rated (4.4/5)