Net material requirements plan using on-hand inventory


Problem: The demand for subassembly S is 100 units in week 7.  Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X.  Finally, each unit of U requires 2 units of Y and 3 units of Z.  One firm manufactures all items.  It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Using this information, construct a net material requirements plan using the following on-hand inventory
 
Item    On-hand inventory
 
S                  20
T                  20
U                  40
V                  30
W                 30
X                  25
Y                 240
Z                  40