Assignment Task: Income recognition for a contractor. On October 15, 2010, Construction Company contracted to build a shopping center at a contract price of $180 million. The schedule of expected and actual cash collections and contract costs is as follows:

Year Cash Collections from Customers Estimated and Actual Cost Incurred

2010 $36,000,000 $12,000,000

2011 $45,000,000 $36,000,000

2012 $45,000,000 $48,000,000

2013 $54,000,000 $24,000,000

$180,000,000 $120,000,000

Q1. How do you get the amount of revenue, expense, and net income for each of the four years under the following revenue recognition methods:

(a) Percentage-of-completion method.

(b) Completed contract method.

Q2. What journal entries company will make in 2010, 2011, 2012, and 2013 for this contract?

Company accumulates contract costs in a Contract in Process account. Although the costs involve a mixture of cash payments, credits to assets, and credits to liability accounts, assume for purposes of this problem that all costs are recorded as credits to Accounts Payable.

Q3. Which method is the better measure of Construction Company's performance under the contract? Why?

Apt tutors are available 24/7 to resolve all the queries with Revenue Recognition Methods Assignment Help service at the most viable prices that no other in the industry can provide.

Tags: Revenue Recognition Methods Assignment Help, Revenue Recognition Methods Homework Help, Revenue Recognition Methods Coursework, Revenue Recognition Methods Solved Assignments, Expected and Actual Cash Assignment Help, Expected and Actual Cash Homework Help, Contract Method Assignment Help, Contract Method Homework Help, Mixture of Cash Payments Assignment Help, Mixture of Cash Payments Homework Help

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Measure of construction company performance
Reference No:- TGS03030960

Expected delivery within 24 Hours