Question: Irving Bonner, an independent computer programming consultant, has contracted to complete eight computer programming jobs. Some jobs must be completed in a certain sequence because they involve program modules that will be linked.

1517_Job time.png

Assume that the current date is Monday, June 1, and that Bonner does not work on weekends. Using Lawler's algorithm, find the sequence in which he should be performing the jobs in order to minimize maximum lateness subject to the precedence constraints.