Instructions calculate the balance of the work in process


Question - Sardin Company begins the month of March with $17,000 of work in process costs from Job 324. Information from job cost sheets shows the following additional costs assigned during March, April, and May of 2008:

Manufacturing Costs Assigned:

Job no.324:

March =$26,000

Job no.325:

March =18,000

April =$23,000

May =$15,000

Job no.326:

March =41,000

April =11,000

Job no.327:

April =16,000

May =31,000

Job no.328:

April =24,000

May =46,000

Job 324 was completed in March. Jobs 325 and 327 were completed in May, and Job 326 was completed in April. Jobs are sold during the month after completion. Total revenue for jobs sold during the 3 month period is $145,000.

Instructions: Calculate the balance of the work in process and finished goods inventory accounts at the end of May.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Instructions calculate the balance of the work in process
Reference No:- TGS02588365

Now Priced at $25 (50% Discount)

Recommended (93%)

Rated (4.5/5)