In anticipation of the original production volume 18000


Materials: 2 yards per unit, $10 per yard

Labor: 0.25 DL hour per unit, $11 per hour

During October, the company experienced an anticipated spike in demand and increased production. Although planned production was for 8000 units, the company actually produced 10,000 units.

In anticipation of the original production volume, 18,000 yards were purchased, at a total cost of $175,000. During the month, 22,000 yards of material were used and 2,400 direct labor hours were worked. Direct labor cost for month totaled $27,000.

Compute the material variance and the quantity variance.

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: In anticipation of the original production volume 18000
Reference No:- TGS01068390

Expected delivery within 24 Hours