In addition to cost what factors should be considered in


Procurement Management

a) In addition to cost, what factors should be considered in selecting a building contractor? What can go wrong if the lowest bid is selected and nothing else is considered? (Answer in your own words, maximum 100 words.)

b) What is the difference between an RFP and an RFQ? Give two specific examples where an RFQ could be used and two specific examples where it is more likely that the organization will go with an RFP. (Use examples NOT from your textbook.)

c) Cost reimbursable contract calculation.

• A contract calls for a total payment of $800,000 with a guarantee. Essentially the contractor is guaranteed to make at least $200,000 above his costs. If the contractor can demonstrate his costs exceed $600,000, the project will pay the difference, with a $50,000 ceiling on the overage. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?

• Another option for the same contract has the contractor guaranteed to be paid his costs plus 20%, for costs that exceed $600,000. With the same initial assumption—guarantee of $800,000 gross payment (no requirement to itemize costs), but if the contractor can show that costs exceed $600,000, the project will pay $800,000 plus the costs that exceed $600,000, plus 20% of those excess costs, with a ceiling of $900,000 gross. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?

• Under the above option, at what dollar amount of total costs would the contractor be assuming all of the excess costs beyond that point?

• In which option did the project assume more of the risk of a cost overrun? Explain.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: In addition to cost what factors should be considered in
Reference No:- TGS01625023

Expected delivery within 24 Hours