If the labor market is perfectly competitive and the market


A new recreational area in a small town will take 20 full-time (40 hours per week) workers 3 weeks to complete. In addition, the cost of materials is expected to be $75,000.

Part A: If the labor market is perfectly competitive and the market wage is $20, what are the total opportunity costs of taking on this project?

Part B: If instead the town had some unemployment, would the opportunity cost of the project change? Explain.

Solution Preview :

Prepared by a verified Expert
Business Economics: If the labor market is perfectly competitive and the market
Reference No:- TGS02332221

Now Priced at $10 (50% Discount)

Recommended (99%)

Rated (4.3/5)