If the internal rate of return irr on a project is 10 and


1) If the payback for project A is 2 years and payback for project B is 5 years, which should you choose using the payback method rules only? (ignore NPV, IRR and any cash flows coming in after paycheck)

A) Choose Project A

B) Choose Project B

C) Choose both because capital budgets allow you to spend as much as you want.

D) Choose neither because you always want a payback of 1 year or less.

2) If the Internal Rate of Return (IRR) on a project is 10% and the cost of capital is 12%, which of the following is true? (assume that this is not a brrowing situation and that there is money in the capital budget for this project)

A) you should accept the project

B) You should reject the project

C) IRR is never a valid measure

D) None of the above is true

Request for Solution File

Ask an Expert for Answer!!
Financial Management: If the internal rate of return irr on a project is 10 and
Reference No:- TGS02355835

Expected delivery within 24 Hours