If project b has the cash flow timeline as year 0 -100 year


If project B has the cash flow timeline as: Year 0 $-100, Year 1 $75, Year 2 $100, Year 3 $300, Year 4 $75, Year 5 $200. Compute the NPV if the cost of capital is 11%.

$292.96

$392.96

$436.18

$466.78