Identify the paths and path duration times -nbsp determine


Given the diagram shown in Figure, with duration times for activities A through L:

a. Identify the paths and path duration times.

b. Determine the critical path.

123_Path Diagram.jpg

Request for Solution File

Ask an Expert for Answer!!
Project Management: Identify the paths and path duration times -nbsp determine
Reference No:- TGS01546038